Solar project GEN-2022-086, Finney County

Solar project GEN-2022-086, Finney County is a 700 MW solar request withdrawn in the SPP interconnection queue, in Finney County, Kansas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2022 (completed)
  2. Withdrawn / abandonedNov 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2022-086
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
345 kV Finney Station
Location
Finney County, Kansas
Technology
Solar: 700 MW
Total requested
700 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
5 November 2022
Proposed online date
December 2027
Withdrawn
November 2023

Location

Marker shows the centre of Finney County; the queue data does not give exact sites.

Power plants in Kansas Β· Transmission lines in Kansas

Other requests in Finney County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem