🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Kansas

SOLAR · SPP

Solar project GEN-2021-023, Grant County

Solar project GEN-2021-023, Grant County is a 306 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Grant County, Kansas, connecting to WERE.

Queue statusConsented
  1. PlanningQueued May 2021 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2030 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2021-023
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WERE
Connection point (POI)
Wild Plains 345kV Substation
Location
Grant County, Kansas
Technology
Solar: 306 MW
Total requested
306 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
14 May 2021
Proposed online date
November 2030

Location

Marker shows the centre of Grant County; the queue data does not give exact sites.

Power plants in Kansas · Transmission lines in Kansas

Other requests in Grant County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem