Solar project GEN-2014-045, Grant County

Solar project GEN-2014-045, Grant County is a 50.0 MW solar request withdrawn in the SPP interconnection queue, in Grant County, Kansas, connecting to SUNC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2014 (completed)
  2. Withdrawn / abandonedNov 2014 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2014-045
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SUNC
Connection point (POI)
Hickok 115kV Sub
Location
Grant County, Kansas
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
29 September 2014
Proposed online date
December 2016
Withdrawn
November 2014

Location

Marker shows the centre of Grant County; the queue data does not give exact sites.

Power plants in Kansas Β· Transmission lines in Kansas

Other requests in Grant County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem