United States › Grid › Interconnection queues › Kansas
SOLAR · SPPSolar project GEN-2021-035, Grant County
Solar project GEN-2021-035, Grant County is a 113 MW solar request in interconnection study in the SPP interconnection queue, in Grant County, Kansas, connecting to SUNC.
Queue statusIn planning
- PlanningQueued May 2021 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2021-035
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SUNC
- Connection point (POI)
- Tap Sunflower Santana 115kV Transmission Line
- Location
- Grant County, Kansas
- Technology
- Solar: 113 MW
- Total requested
- 113 MW
- Service type
- Energy only (ERIS)
- Study phase
- FACILITY STUDY STAGE
- Queue status
- Active
- Entered queue
- 14 May 2021
- Proposed online date
- December 2026
Location
Marker shows the centre of Grant County; the queue data does not give exact sites.
Other requests in Grant County
- Solar project GEN-2021-023, Grant CountySolar · 306 MW · agreement signed
- Gas project GEN-2012-007, Grant CountyGas · 120 MW · built
- Battery storage project GEN-2023-175, Grant CountyBattery storage · 200 MW · withdrawn
- Solar project GEN-2017-110, Grant CountySolar · 100 MW · withdrawn
- Solar project GEN-2014-045, Grant CountySolar · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem