United States › Grid › Interconnection queues › Kansas
SOLAR · SPPSolar project GEN-2017-184, Hodgeman County
Solar project GEN-2017-184, Hodgeman County is a 400 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Hodgeman County, Kansas, connecting to KCPL.
Queue statusConsented
- PlanningQueued Nov 2017 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Jan 2029 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GEN-2017-184
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- KCPL
- Connection point (POI)
- Nashua-St. Joe 345kV
- Location
- Hodgeman County, Kansas
- Technology
- Solar: 400 MW
- Total requested
- 400 MW
- Service type
- NRIS and ERIS
- Study phase
- IA FULLY EXECUTED/ON SCHEDULE
- Queue status
- Active
- Entered queue
- 29 November 2017
- Proposed online date
- January 2029
Location
Marker shows the centre of Hodgeman County; the queue data does not give exact sites.
Other requests in Hodgeman County
- Onshore wind project GEN-2017-183, Hodgeman CountyOnshore wind · 400 MW · agreement signed
- Onshore wind project GEN-2021-070, Hodgeman CountyOnshore wind · 504 MW · in study
- Onshore wind project GEN-2021-069, Hodgeman CountyOnshore wind · 250 MW · in study
- Onshore wind project GEN-2021-068, Hodgeman CountyOnshore wind · 250 MW · in study
- Onshore wind project GEN-2011-017, Hodgeman CountyOnshore wind · 299 MW · withdrawn
- Onshore wind project GEN-2011-016, Hodgeman CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project GEN-2010-015, Hodgeman CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project GEN-2010-054, Hodgeman CountyOnshore wind · 200 MW · withdrawn
- Solar project GEN-2017-049, Hodgeman CountySolar · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem