ONSHORE WIND Β· SPP

Onshore wind project GEN-2011-017, Hodgeman County

Onshore wind project GEN-2011-017, Hodgeman County is a 299 MW onshore wind request withdrawn in the SPP interconnection queue, in Hodgeman County, Kansas, connecting to SUNC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2011 (completed)
  2. Withdrawn / abandonedSep 2015 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingJan 2018 (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2011-017
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SUNC
Connection point (POI)
Tap Spearville - Knoll 345kV
Location
Hodgeman County, Kansas
Technology
Wind: 299 MW
Total requested
299 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
31 March 2011
Proposed online date
January 2018
Came online
January 2018
Withdrawn
September 2015

Location

Marker shows the centre of Hodgeman County; the queue data does not give exact sites.

Power plants in Kansas Β· Transmission lines in Kansas

Other requests in Hodgeman County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem