🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New York

SOLAR · NYISO

White Creek Solar

White Creek Solar is a 135 MW solar request in interconnection study in the NYISO interconnection queue, in Livingston County, New York, connecting to RG&E.

Queue statusIn planning
  1. PlanningQueued Nov 2018 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
777
Grid region
NYISO (New York)
Utility / transmission owner
RG&E
Developer
White Creek Solar, LLC
Connection point (POI)
Sta 82 - Sta 128 115kV
Location
Livingston County, New York
Technology
Solar: 135 MW
Total requested
135 MW
Study phase
SRIS, FS
Queue status
Active
Entered queue
1 November 2018
Proposed online date
June 2028

Location

Marker shows the centre of Livingston County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Livingston County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem