SOLAR · NYISO

Horseshoe Solar

Horseshoe Solar is a 180 MW solar request in interconnection study in the NYISO interconnection queue, in Livingston County, New York, connecting to NM-NG.

Queue statusIn planning
  1. PlanningQueued May 2018 (current stage)
  2. ConsentedJan 2023 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
710
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
Horseshoe Solar Energy LLC
Connection point (POI)
Golah 115kV
Location
Livingston County, New York
Technology
Solar: 180 MW
Total requested
180 MW
Study phase
FES, FS
Queue status
Active
Entered queue
29 May 2018
Agreement signed
11 January 2023
Proposed online date
May 2028

Location

Marker shows the centre of Livingston County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Livingston County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem