United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Interconnection queue in the USA (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown589109.2 GW
Active in queue109.2 GW589 requests
Agreement signed64.3 GW347 requests
Withdrawn1,473226.5 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

589 requests ยท page 1 of 12
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project Q68, Los Angeles County
Solar + storage
2,400 MWIn study Los Angeles, CAWest Mar 2019target 2022
Angeleno Solar Farm
Solar + storage
2,300 MWAgreement signed Los Angeles, CACAISO Apr 2019target 2028
Sanborn Hybrid 3
Solar + storage
2,159 MWAgreement signed Kern, CACAISO Apr 2019target 2026
Buttonbush Solar Hybrid Energy Center
Solar + storage
1,636 MWAgreement signed Kern, CACAISO Apr 2019target 2026
Onshore wind project Q320, San Juan County
Onshore wind
1,500 MWPaused / redesign San Juan, NMWest Sep 2019target 2026
Arida 2 Solar Farm
Solar + storage
1,400 MWIn study Clark, NVCAISO Apr 2019target 2029
Bay State Wind 4 Offshore Wind
Offshore wind
1,200 MWAgreement signed MAISO-NE Dec 2019target 2033
Solar + storage project G0615, Sherman County
Solar + storage
1,200 MWIn study Sherman, ORWest Feb 2019target 2021
Oberon
Solar + storage
1,037 MWAgreement signed Riverside, CACAISO Apr 2019target 2026
Onshore wind project GI-83, Randolph County
Onshore wind
1,018 MWAgreement signed Randolph, MOSoutheast Jun 2019target 2027
Bellefield 2 Solar Farm
Solar + storage
1,000 MWAgreement signed Kern, CACAISO Apr 2019target 2024
Pelicans Jaw Hybrid Solar
Solar + storage
1,000 MWAgreement signed Kings, CACAISO Apr 2019target 2028
Other project J1490, Randolph County
Other
1,000 MWAgreement signed Randolph, MOMISO Apr 2019target 2024
Onshore wind project Q318, San Juan County
Onshore wind
1,000 MWPaused / redesign San Juan, NMWest Sep 2019target 2026
Onshore wind project Q319, San Juan County
Onshore wind
1,000 MWPaused / redesign San Juan, NMWest Sep 2019target 2026
Hoodini
Solar + storage
910 MWIn study Yuma, AZCAISO Apr 2019target 2028
Cvow 2, Oss 2 โ€šร„รฌ T2G07
Offshore wind ยท Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
836 MWIn study City Of Chesapeake, VAPJM Sep 2019target 2032
Cvow 1, Oss 1 - T1L11
Offshore wind ยท Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
833 MWIn study City Of Chesapeake, VAPJM Sep 2019target 2032
Cvow 3, Oss 3 โ€šร„รฌ T3G15
Offshore wind ยท Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
820 MWIn study City Of Chesapeake, VAPJM Sep 2019target 2032
Lycan Solar
Solar + storage
800 MWAgreement signed Riverside, CACAISO Apr 2019target 2030
Calypso Solar
Solar + storage
800 MWAgreement signed Riverside, CACAISO Apr 2019target 2031
Irving Storage
Battery storage
783 MWAgreement signed Monterey, CACAISO May 2019target 2025
Other project Company KD, White Pine County
Other
750 MWPaused / redesign White Pine, NVWest Sep 2019target 2026
Solar + storage project Q317, Coconino County
Solar + storage
750 MWIn study Coconino, AZWest Sep 2019target 2023
Gas project J1246, Iberville Parish County
Gas
725 MWAgreement signed Iberville Parish, LAMISO Apr 2019target 2025
Kingsley Solar Farm
Solar + storage
720 MWAgreement signed Imperial, CACAISO Apr 2019target 2030
Menifee Power Bank
Battery storage
680 MWAgreement signed Riverside, CACAISO Apr 2019target 2025
Bonanza Peak Solar Farm
Solar + storage
641 MWAgreement signed Clark, NVCAISO Apr 2019target 2027
Bonanza Solar
Solar + storage
600 MWAgreement signed Clark, NVCAISO Apr 2019target 2028
Onshore wind project 366, Rosebud County
Onshore wind
600 MWPaused / redesign Rosebud, MTWest Sep 2019target 2022
Onshore wind project C006, Wheatland County
Onshore wind
600 MWIn study Wheatland, MTWest Feb 2019target 2021
Onshore wind project 82, Meagher County
Onshore wind
600 MWAgreement signed Meagher, MTWest Feb 2019
Onshore wind project 361, Wheatland County
Onshore wind
600 MWIn study Wheatland, MTWest Mar 2019target 2021
Gas project 401, Humphreys County
Gas
593 MWAgreement signed Humphreys, TNSoutheast Sep 2019target 2023
Chesterfield CT Units 3&4
Gas
569 MWAgreement signed Chesterfield, VAPJM Sep 2019target 2029
Chesterfield CT Units 1 and 2
Gas ยท Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
569 MWIn study Chesterfield, VAPJM Sep 2019target 2029
Yellow Pine 3
Solar + storage
517 MWAgreement signed Clark, NVCAISO Apr 2019target 2026
Renegade Project
Solar ยท Renegade Renewable LLC
516 MWAgreement signed Deaf Smith, TXERCOT Feb 2019target 2027
Double Butte Storage
Battery storage
508 MWAgreement signed Riverside, CACAISO Apr 2019target 2030
Harley Hand Solar
Solar + storage ยท HECTATE ENERGY HARLEY HAND SOLAR LLC
506 MWIn study Nolan, TXERCOT Dec 2019target 2029
Wind + storage project Q311, Navajo County
Wind + storage
500 MWIn study Navajo, AZWest Sep 2019target 2021
Solar + storage project Q28, Maricopa County
Solar + storage
500 MWIn study Maricopa, AZWest Oct 2019target 2027
Onshore wind project G0619, Wasco County
Onshore wind
500 MWIn study Wasco, ORWest Apr 2019target 2023
Other project J1488, Randolph County
Other
500 MWAgreement signed Randolph, MOMISO Apr 2019target 2024
Solar + storage project Q67, Clark County
Solar + storage
500 MWIn study Clark, NVWest Mar 2019target 2022
Randolph Solar
Solar ยท Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
500 MWAgreement signed Halifax, VAPJM Dec 2019target 2032
Cider Solar
Solar ยท Hecate Energy Cider Solar LLC
500 MWIn study Genesee, NYNYISO Apr 2019target 2027
Solar + storage project IA-PNM-2019-11, San Juan County
Solar + storage ยท 450CT 8ME
500 MWAgreement signed San Juan, NMWest Apr 2019target 2025
Goldback Solar Center
Battery storage
500 MWAgreement signed Ventura, CACAISO Apr 2019target 2026
Solar project Q312, Coconino County
Solar
500 MWIn study Coconino, AZWest Sep 2019target 2021
Page 1 of 12

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)