United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESInterconnection queue in the USA (2025 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Schahfer CCGTs Gas · NIPSCO |
2,740 MW | In study |
| Gas project J3996, St. Charles County Gas |
2,220 MW | In study |
| Gas project AG2-582, Doddridge County Gas · CPV Shay, LLC |
2,100 MW | In study |
| Prairie Ridge (Gas - CC) Gas · Tenaska Power Generation, LLC |
1,660 MW | In study |
| Richland Parish generators Gas · Entergy Louisiana, LLC |
1,640 MW | In study |
| Richland Parish generators Gas · Entergy Louisiana, LLC |
1,640 MW | In study |
| Franklin Farms Gas · Entergy Louisiana, LLC |
1,640 MW | In study |
| Gas project 977726, Rowan County Gas |
1,620 MW | In study |
| Gas project J3999, Vermillion County Gas |
1,540 MW | In study |
| Gas project J4071, Livingston Parish County Gas |
1,500 MW | In study |
| Caldwell County Energy Center Gas · Caldwell County Energy Center, LLC |
1,500 MW | In study |
| Big Canyon Wind Onshore wind · Longfellow Wind, LLC |
1,500 MW | In study |
| Gas project J4024, Monroe County Gas |
1,499 MW | In study |
| Gas project J4025, Monroe County Gas |
1,499 MW | In study |
| Gas project J3922, Branch County Gas |
1,445 MW | In study |
| Gas project J3923, Washtenaw County Gas |
1,414 MW | In study |
| Gas project GEN-2024-340, Creek County Gas |
1,400 MW | In study |
| Gas project 977731, Davidson County Gas |
1,395 MW | In study |
| Mule Deer Run Gas Gas · BOULEVARD ASSOCIATES, LLC |
1,381 MW | In study |
| Gas project GEN-2024-377, Harrison County Gas |
1,350 MW | In study |
| Gas project GEN-2024-379, Bossier Parish County Gas |
1,350 MW | In study |
| Gas project J4113, Cerro Gordo County Gas |
1,315 MW | In study |
| Gas project GEN-2024-132, Johnston County Gas |
1,300 MW | In study |
| Gas project AH1-680, Carroll County Gas · Chestnut Run Energy LLC |
1,300 MW | In study |
| Solar + storage project T2-082, Klamath County Solar + storage |
1,280 MW | In study |
| Solar + storage project T2-081, Harney County Solar + storage |
1,280 MW | In study |
| Jewett Energy Center 1 Gas Gas · Jewett Energy Center LLC |
1,274 MW | In study |
| Gas project J3935, Genesee County Gas |
1,268 MW | In study |
| Tolar Energy Center Gas · NRG Tolar Power LLC |
1,252 MW | In study |
| Limitless Energy Hub I Gas · Limitless Energy Hub I LLC |
1,238 MW | In study |
| Limitless Energy Hub II Gas · Limitless Energy Hub II LLC |
1,238 MW | In study |
| Red Oak Ridge Energy Center Gas · Invenergy |
1,211 MW | In study |
| Gas project E0016, Calumet County Gas · Invenergy |
1,211 MW | In study |
| Wolf Bone North Energy Center Gas · NRG Wolf Bone Energy Center LLC |
1,204 MW | In study |
| Gas project J4164, Dane County Gas |
1,203 MW | In study |
| Gas project J4165, Kenosha County Gas |
1,203 MW | In study |
| Gas project J4014, Calumet County Gas |
1,203 MW | In study |
| Spectra Solar Solar · SE DC Devco |
1,200 MW | In study |
| Gas project J3941, Deuel County Gas |
1,144 MW | In study |
| Malden CCGT Gas · NIPSCO |
1,090 MW | In study |
| Gas project GEN-2024-341, Pittsburg County Gas |
1,045 MW | In study |
| Zeus Scurry BESS Solar + storage · Zeus Scurry BESS |
1,043 MW | In study |
| Zeus Mitchell BESS II Solar + storage · Zeus Mitchell BESS II, LLC |
1,043 MW | In study |
| Kickstart Energy Storage VI Battery storage · Kickstart Infrastructure LLC |
1,026 MW | In study |
| Other project Q617, Mohave County Other |
1,000 MW | In study |
| Solar + storage project 25-00394, Esmerelda County Solar + storage |
1,000 MW | In study |
| Solar project J4161, Watonwan County Solar |
1,000 MW | In study |
| Gas project 25-00427, Storey County Gas |
1,000 MW | In study |
| Solar + storage project G1087, Yakima County Solar + storage |
1,000 MW | In study |
| Kickstart Energy Storage V Battery storage · Kickstart Infrastructure LLC |
999 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- MISO (Midcontinent)390 · 120.8 GW
- ERCOT (Texas)361 · 104.0 GW
- West (non-ISO utilities)325 · 84.1 GW
- SPP (Southwest Power Pool)268 · 71.3 GW
- Southeast (non-ISO utilities)264 · 42.0 GW
- PJM (Mid-Atlantic, Midwest)228 · 29.8 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)