🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Oklahoma

GAS · SPP

Gas project GEN-2024-340, Creek County

Gas project GEN-2024-340, Creek County is a 1,400 MW gas request in interconnection study in the SPP interconnection queue, in Creek County, Oklahoma, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2032 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2024-340
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Riverside – Redbud 345 kV line
Location
Creek County, Oklahoma
Technology
Gas: 1,400 MW
Total requested
1,400 MW
Service type
NRIS and ERIS
Study phase
DISIS STAGE
Queue status
Active
Entered queue
1 March 2025
Proposed online date
January 2032

Location

Marker shows the centre of Creek County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Creek County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem