United States › Grid › Interconnection queues › Oklahoma
BATTERY STORAGE · SPPBattery storage project GEN-2024-SR5, Creek County
Battery storage project GEN-2024-SR5, Creek County is a 177 MW battery storage request with a signed interconnection agreement in the SPP interconnection queue, in Creek County, Oklahoma, connecting to OG&E.
Queue statusConsented
- PlanningQueued Feb 2024 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Jun 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GEN-2024-SR5
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- OG&E
- Connection point (POI)
- 138 kV Greenwood Station
- Location
- Creek County, Oklahoma
- Technology
- Battery: 177 MW
- Total requested
- 177 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA FULLY EXECUTED/ON SCHEDULE
- Queue status
- Active
- Entered queue
- 7 February 2024
- Proposed online date
- June 2026
Location
Marker shows the centre of Creek County; the queue data does not give exact sites.
Other requests in Creek County
- Gas project GI-103, Creek CountyGas · 460 MW · agreement signed
- Gas project GEN-2024-340, Creek CountyGas · 1,400 MW · in study
- Battery storage project GEN-2022-156, Creek CountyBattery storage · 100 MW · in study
- Battery storage project GEN-2024-169, Creek CountyBattery storage · 140 MW · withdrawn
- Gas project GI-125, Creek CountyGas · 85.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem