United States › Grid › Interconnection queues › Oklahoma
BATTERY STORAGE · SPPBattery storage project GEN-2022-156, Creek County
Battery storage project GEN-2022-156, Creek County is a 100 MW battery storage request in interconnection study in the SPP interconnection queue, in Creek County, Oklahoma, connecting to GRDA.
Queue statusIn planning
- PlanningQueued Feb 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2022-156
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- GRDA
- Connection point (POI)
- Silver City 138 kV Substation
- Location
- Creek County, Oklahoma
- Technology
- Battery: 100 MW
- Total requested
- 100 MW
- Service type
- Energy only (ERIS)
- Study phase
- FACILITY STUDY STAGE
- Queue status
- Active
- Entered queue
- 24 February 2023
- Proposed online date
- December 2027
Location
Marker shows the centre of Creek County; the queue data does not give exact sites.
Other requests in Creek County
- Gas project GI-103, Creek CountyGas · 460 MW · agreement signed
- Battery storage project GEN-2024-SR5, Creek CountyBattery storage · 177 MW · agreement signed
- Gas project GEN-2024-340, Creek CountyGas · 1,400 MW · in study
- Battery storage project GEN-2024-169, Creek CountyBattery storage · 140 MW · withdrawn
- Gas project GI-125, Creek CountyGas · 85.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem