United States › Grid › Interconnection queues › Texas
GAS · ERCOTJewett Energy Center 1 Gas
Jewett Energy Center 1 Gas is a 1,274 MW gas request in interconnection study in the ERCOT interconnection queue, in Freestone County, Texas.
Queue statusIn planning
- PlanningQueued Oct 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Nov 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 29INR0150
- Grid region
- ERCOT (Texas)
- Developer
- Jewett Energy Center LLC
- Connection point (POI)
- Tap #3391 JEWETT_N5 - #46020 LMEST_POI_5 and Tap #3390 JEWETT_S5 - #46020 LMEST_POI_5
- Location
- Freestone County, Texas
- Technology
- Gas: 1,274 MW
- Total requested
- 1,274 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 21 October 2025
- Proposed online date
- November 2029
Location
Marker shows the centre of Freestone County; the queue data does not give exact sites.
Other requests in Freestone County
- Piedra SolarSolar + storage · 282 MW · agreement signed
- Pin Peaking Energy Center 1 (TEF- Due Diligence)Gas · 228 MW · agreement signed
- Pin Peaking Energy Center 2 (TEF- Due Diligence)Gas · 228 MW · agreement signed
- Bar Candela Solar SLFSolar + storage · 200 MW · agreement signed
- Fairway StorageBattery storage · 120 MW · agreement signed
- Piedra BESSSolar + storage · 104 MW · agreement signed
- Silver Dollar SolarSolar + storage · 302 MW · in study
- Amerada SolarSolar + storage · 302 MW · in study
- Simsboro StorageBattery storage · 302 MW · in study
- Douie SolarSolar · 221 MW · in study
- Freestone Battery Storage ProjectBattery storage · 211 MW · in study
- Avant Prairie BESSBattery storage · 202 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem