GAS · ERCOTPin Peaking Energy Center 1 (TEF- Due Diligence)
Pin Peaking Energy Center 1 (TEF- Due Diligence) is a 228 MW gas request with a signed interconnection agreement in the ERCOT interconnection queue, in Freestone County, Texas.
Queue statusConsented
- PlanningQueued Apr 2023 (completed)
- ConsentedMay 2024 (current stage)
- Construction (not yet reached)
- OperatingTarget May 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 26INR0049
- Grid region
- ERCOT (Texas)
- Developer
- PIN OAK CREEK ENERGY CENTER, LLC
- Connection point (POI)
- 3134 RICHLAND CHAMBERS 345kV (PSS/E Bus Name: RICHLND1_5)
- Location
- Freestone County, Texas
- Technology
- Gas: 228 MW
- Total requested
- 228 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 19 April 2023
- Agreement signed
- 30 May 2024
- Proposed online date
- May 2026
Location
Marker shows the centre of Freestone County; the queue data does not give exact sites.
Other requests in Freestone County
- Piedra SolarSolar + storage · 282 MW · agreement signed
- Pin Peaking Energy Center 2 (TEF- Due Diligence)Gas · 228 MW · agreement signed
- Bar Candela Solar SLFSolar + storage · 200 MW · agreement signed
- Fairway StorageBattery storage · 120 MW · agreement signed
- Piedra BESSSolar + storage · 104 MW · agreement signed
- Jewett Energy Center 1 GasGas · 1,274 MW · in study
- Silver Dollar SolarSolar + storage · 302 MW · in study
- Amerada SolarSolar + storage · 302 MW · in study
- Simsboro StorageBattery storage · 302 MW · in study
- Douie SolarSolar · 221 MW · in study
- Freestone Battery Storage ProjectBattery storage · 211 MW · in study
- Avant Prairie BESSBattery storage · 202 MW · in study