Pin Peaking Energy Center 1 (TEF- Due Diligence)

Pin Peaking Energy Center 1 (TEF- Due Diligence) is a 228 MW gas request with a signed interconnection agreement in the ERCOT interconnection queue, in Freestone County, Texas.

Queue statusConsented
  1. PlanningQueued Apr 2023 (completed)
  2. ConsentedMay 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
26INR0049
Grid region
ERCOT (Texas)
Developer
PIN OAK CREEK ENERGY CENTER, LLC
Connection point (POI)
3134 RICHLAND CHAMBERS 345kV (PSS/E Bus Name: RICHLND1_5)
Location
Freestone County, Texas
Technology
Gas: 228 MW
Total requested
228 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
19 April 2023
Agreement signed
30 May 2024
Proposed online date
May 2026

Location

Marker shows the centre of Freestone County; the queue data does not give exact sites.