United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Interconnection queue in the USA (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,249298.6 GW
Active in queue298.6 GW1,249 requests
Agreement signed34.6 GW168 requests
Withdrawn2,063551.8 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,249 requests ยท page 1 of 25
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project G1052, Deschutes County
Solar + storage
2,600 MWIn study Deschutes, ORWest Nov 2023target 2030
Solar + storage project G1051, Deschutes County
Solar + storage
2,600 MWIn study Deschutes, ORWest Nov 2023target 2030
Muon
Solar + storage
2,339 MWIn study Fresno, CACAISO Apr 2023target 2028
Offshore wind project AI2-431, Atlantic County
Offshore wind
2,139 MWIn study Atlantic, NJPJM Mar 2023target 2030
Stanley
Solar + storage
2,071 MWIn study Maricopa, AZCAISO Apr 2023target 2030
Quark
Solar + storage
2,045 MWIn study Fresno, CACAISO Apr 2023target 2028
Ripple
Solar + storage
1,880 MWIn study Kings, CACAISO Apr 2023target 2031
Hecate Energy Orem Wind
Onshore wind ยท Hecate Energy LLC
1,542 MWIn study Brazoria, TXERCOT Jun 2023target 2030
Solar + storage project Q98, Los Angeles County
Solar + storage
1,500 MWIn study Los Angeles, CAWest Mar 2023target 2030
Sunflower
Solar + storage
1,430 MWIn study San Bernardino, CACAISO Apr 2023target 2031
Offshore wind project AJ1-015, Monmouth County
Offshore wind
1,342 MWIn study Monmouth, NJPJM Jun 2023target 2030
Broadview
Solar + storage
1,308 MWIn study Fresno, CACAISO Apr 2023target 2028
Other project G0864, Sherman County
Other
1,304 MWIn study Sherman, ORWest May 2023target 2027
Battery storage project G1053, Crook County
Battery storage
1,300 MWIn study Crook, ORWest Nov 2023target 2031
Battery storage project G1055, Wasco County
Battery storage
1,300 MWIn study Wasco, ORWest Nov 2023target 2032
Battery storage project G1054, Crook County
Battery storage
1,300 MWIn study Crook, ORWest Nov 2023target 2031
Solar + storage project G1050, Deschutes County
Solar + storage
1,300 MWIn study Deschutes, ORWest Nov 2023target 2028
Other project G1025, Douglas County
Other
1,274 MWIn study Douglas, WAWest Nov 2023target 2029
Matterhorn
Other
1,218 MWIn study Riverside, CACAISO Apr 2023target 2029
Solstice B
Solar + storage
1,211 MWIn study Fresno, CACAISO Apr 2023target 2031
Solar + storage project Q105, Millard County
Solar + storage ยท Intermountain Power Agency
1,200 MWIn study Millard, UTWest Jun 2023target 2028
Aviation
Gas
1,200 MWIn study San Bernardino, CACAISO Apr 2023target 2028
Pion
Battery storage
1,168 MWIn study Fresno, CACAISO Apr 2023target 2028
Aurelius Solar
Solar ยท IP Roman, LLC
1,124 MWAgreement signed Deaf Smith, TXERCOT Jul 2023target 2028
Battery storage project AI2-457, Charles County
Battery storage
1,122 MWIn study Charles, MDPJM Mar 2023target 2027
Nuclear project G0998, Benton County
Nuclear
1,120 MWIn study Benton, WAWest Nov 2023target 2030
Solstice A
Solar + storage
1,111 MWIn study Fresno, CACAISO Apr 2023target 2031
Hillside Energy Storage
Battery storage
1,065 MWIn study Los Angeles, CACAISO Apr 2023target 2029
Musketeers
Solar + storage
1,047 MWIn study Tulare, CACAISO Apr 2023target 2029
Hecate Energy Arkansas Wind
Onshore wind ยท Hecate Energy Gulf Wind LLC
1,029 MWIn study San Patricio, TXERCOT Jun 2023target 2030
Hecate Energy Jamaica Wind
Onshore wind ยท Hecate Energy LLC
1,029 MWIn study Galveston, TXERCOT Jun 2023target 2030
Crusade
Battery storage
1,029 MWIn study Orange, CACAISO Apr 2023target 2028
Lagoonez
Battery storage
1,029 MWIn study Los Angeles, CACAISO Apr 2023target 2028
Ross Solar
Solar + storage ยท S&S Renewables, LLC
1,026 MWAgreement signed Refugio, TXERCOT Jul 2023target 2027
Battery storage project G0914, Douglas County
Battery storage
1,000 MWIn study Douglas, WAWest Jul 2023target 2028
Solar + storage project Company 238, Nye County
Solar + storage
1,000 MWIn study Nye, NVWest Jan 2023target 2028
Solar + storage project Q96, Los Angeles County
Solar + storage
1,000 MWIn study Los Angeles, CAWest Mar 2023target 2030
Alisa Solar Energy Complex 2
Solar + storage
1,000 MWIn study Yuma, AZCAISO Apr 2023target 2030
Wind + storage project Q101, Los Angeles County
Wind + storage
1,000 MWIn study Los Angeles, CAWest Apr 2023target 2030
Solar + storage project Q97, Los Angeles County
Solar + storage
1,000 MWIn study Los Angeles, CAWest Mar 2023target 2030
Wind + storage project Q100, Los Angeles County
Wind + storage
1,000 MWIn study Los Angeles, CAWest Apr 2023target 2030
Gas project Q32, Pinal County
Gas
928 MWIn study Pinal, AZWest Aug 2023target 2026
Bristlecone
Solar + storage
921 MWIn study Nye, NVCAISO Apr 2023target 2030
Gas project GEN-2023-204, Morris County
Gas
915 MWIn study Morris, TXSPP Oct 2023target 2028
Amanece
Solar + storage
836 MWIn study Stanislaus, CACAISO Apr 2023target 2029
Carissalito Creek
Solar + storage
832 MWIn study Merced, CACAISO Apr 2023target 2030
Maravillosa 2
Solar + storage
812 MWIn study Kern, CACAISO Apr 2023target 2029
Solar + storage project G1040, Benton County
Solar + storage
800 MWIn study Benton, WAWest Nov 2023target 2030
Battery storage project Company 257, Clark County
Battery storage
800 MWIn study Clark, NVWest Sep 2023target 2026
Solar + storage project Q38, Maricopa County
Solar + storage
800 MWIn study Maricopa, AZWest Feb 2023target 2027
Page 1 of 25

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)