BATTERY STORAGE · PJM

Battery storage project AI2-457, Charles County

Battery storage project AI2-457, Charles County is a 1,122 MW battery storage request in interconnection study in the PJM interconnection queue, in Charles County, Maryland, connecting to PEPCO.

Queue statusIn planning
  1. PlanningQueued Mar 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AI2-457
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PEPCO
Connection point (POI)
Morgantown 230 kV
Location
Charles County, Maryland
Technology
Battery: 1,122 MW
Total requested
1,122 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
11 March 2023
Proposed online date
October 2027

Location

Marker shows the centre of Charles County; the queue data does not give exact sites.

Power plants in Maryland · Transmission lines in Maryland

Other requests in Charles County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem