SOLAR · PJM

Solar project AH2-266, Charles County

Solar project AH2-266, Charles County is a 25.0 MW solar request in interconnection study in the PJM interconnection queue, in Charles County, Maryland, connecting to SMECO.

Queue statusIn planning
  1. PlanningQueued Mar 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AH2-266
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
SMECO
Connection point (POI)
Hughesville-Cedarville 69kV
Location
Charles County, Maryland
Technology
Solar: 25.0 MW
Total requested
25.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
10 March 2022
Proposed online date
March 2026

Location

Marker shows the centre of Charles County; the queue data does not give exact sites.

Power plants in Maryland · Transmission lines in Maryland

Other requests in Charles County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem