CPV Maryland

CPV Maryland is a 75.0 MW gas request built and operating in the PJM interconnection queue, in Charles County, Maryland, connecting to PEPCO.

Queue statusOperating
  1. PlanningQueued Sep 2017 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingMar 2019 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AD1-114
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PEPCO
Connection point (POI)
Kelson Ridge 230kV
Location
Charles County, Maryland
Technology
Gas: 75.0 MW
Total requested
75.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
26 September 2017
Proposed online date
May 2021
Came online
March 2019

Location

Marker shows the centre of Charles County; the queue data does not give exact sites.

Power plants in Maryland Β· Transmission lines in Maryland

Other requests in Charles County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem