United States › Grid › Interconnection queues › Texas
SOLAR + STORAGE · ERCOTRoss Solar
Ross Solar is a 1,026 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Refugio County, Texas.
Queue statusConsented
- PlanningQueued Jul 2023 (completed)
- ConsentedJun 2024 (current stage)
- Construction (not yet reached)
- OperatingTarget Jul 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 26INR0155
- Grid region
- ERCOT (Texas)
- Developer
- S&S Renewables, LLC
- Connection point (POI)
- tap 345kV 8249 Angstrom – 8676 Static
- Location
- Refugio County, Texas
- Technology
- Solar: 1,026 MW · Battery
- Total requested
- 1,026 MW
- Study phase
- SS Completed, FIS Started, IA
- Queue status
- Active
- Entered queue
- 31 July 2023
- Agreement signed
- 27 June 2024
- Proposed online date
- July 2027
Location
Marker shows the centre of Refugio County; the queue data does not give exact sites.
Other requests in Refugio County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem