United States › Grid › Interconnection queues › Texas

ONSHORE WIND · ERCOT

Cranel Wind

Cranel Wind is a 220 MW onshore wind request built and operating in the ERCOT interconnection queue, in Refugio County, Texas.

Queue statusOperating
  1. PlanningQueued Sep 2017 (completed)
  2. ConsentedOct 2018 (completed)
  3. Construction (completed)
  4. OperatingJan 2022 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
19INR0112
Grid region
ERCOT (Texas)
Developer
Eon
Connection point (POI)
tap 345kV 8164 Coleto - 8455 Lon Hill
Location
Refugio County, Texas
Technology
Wind: 220 MW
Total requested
220 MW
Study phase
IA
Queue status
Operational
Entered queue
11 September 2017
Agreement signed
12 October 2018
Proposed online date
February 2022
Came online
January 2022

Location

Marker shows the centre of Refugio County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Refugio County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem