United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTMobee Springs BESS
Mobee Springs BESS is a 101 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Refugio County, Texas.
Queue statusIn planning
- PlanningQueued Jun 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Mar 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 28INR0175
- Grid region
- ERCOT (Texas)
- Developer
- Mobee Springs, LLC
- Connection point (POI)
- #8805 BONIVIEW2A 69kV
- Location
- Refugio County, Texas
- Technology
- Battery: 101 MW
- Total requested
- 101 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 5 June 2025
- Proposed online date
- March 2028
Location
Marker shows the centre of Refugio County; the queue data does not give exact sites.
Other requests in Refugio County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem