United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Ross Storage

Ross Storage is a 511 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Refugio County, Texas.

Queue statusConsented
  1. PlanningQueued Aug 2023 (completed)
  2. ConsentedJun 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
26INR0156
Grid region
ERCOT (Texas)
Developer
S&S Renewables, LLC
Connection point (POI)
tap the 345 kV Angstrom (#8249) – Static (#8676) line; AEP
Location
Refugio County, Texas
Technology
Battery: 511 MW · Battery
Total requested
511 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
14 August 2023
Agreement signed
27 June 2024
Proposed online date
July 2027

Location

Marker shows the centre of Refugio County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Refugio County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem