Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,283285.2 GW
Active in queue285.2 GW1,283 requests
Agreement signed30.3 GW117 requests
Withdrawn1,313251.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,283 requests · page 1 of 26
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project Q2409, Navajo County
Solar + storage
2,626 MWIn study Navajo, AZWest Feb 2024target 2028
Smarr CC
Gas
2,000 MWIn study Monroe, GASoutheast Aug 2024target 2028
Gas project 628, Todd County
Gas
1,600 MWIn study Todd, KYSoutheast Jun 2024target 2030
Gas project 620, Trousdale County
Gas
1,600 MWIn study Trousdale, TNSoutheast Jun 2024target 2031
Aegle Power
Gas · Aegle Power LLC
1,536 MWIn study Cameron, TXERCOT Jul 2024target 2027
Gas project 958347, Person County
Gas · Duke Energy Progress, LLC
1,455 MWIn study Person, NCSoutheast Jun 2024
Gas project J3799, Livingston County
Gas
1,452 MWIn study Livingston, MIMISO Apr 2024target 2030
Gas project 957264, Anderson County
Gas
1,450 MWIn study Anderson, SCSoutheast Jun 2024
Vineyard Mid-Atlantic West
Offshore wind · Vineyard Mid-Atlantic LLC
1,321 MWIn study Nassau, NYNYISO Aug 2024target 2032
Bluepoint Wind 1
Offshore wind · Bluepoint Wind LLC
1,310 MWIn study Kings, NYNYISO Aug 2024target 2033
Other project Q572, Riverside County
Other
1,300 MWIn study Riverside, CAWest May 2024target 2031
Sandow Lakes Energy Station
Gas · SL Energy Power Plant I, LLC
1,292 MWIn study Milam, TXERCOT Mar 2024target 2028
Replacing 464.5 MW Steam/Gas with 97.8 MW Steam; DOW Chem
Gas
1,232 MWIn study Iberville, LAMISO May 2024target 2025
Corvette Wind
Onshore wind
1,200 MWPaused / redesign Carson, TXERCOT Feb 2024
Replacement; Oak Creek Units 5-8
Gas
1,138 MWIn study Milwaukee, WIMISO Jun 2024target 2027
Bastrop Peaking Generators (TEF-Due Diligence)
Gas · MPH Bastrop Peakers, LLC
1,104 MWAgreement signed Bastrop, TXERCOT Feb 2024target 2027
Zeus Armstrong BESS
Solar + storage · Armstrong BESS, LLC
1,043 MWIn study Armstrong, TXERCOT Mar 2024target 2028
Zeus Mitchell BESS
Solar + storage · Mitchell BESS
1,043 MWIn study Mitchell, TXERCOT May 2024target 2029
Replacing 1014.7 MW of coal generation with Gas/Steam; Cayuga CC1 CC2
Gas
1,040 MWIn study Vermillion, INMISO Feb 2024target 2028
EmberGreen
Gas · EmberGreen Energy Center
1,036 MWIn study Wharton, TXERCOT Jun 2024target 2028
Battery storage project Q2405, Maricopa County
Battery storage
1,020 MWIn study Maricopa, AZWest Feb 2024target 2033
Gas project IC-1254b, Heard County
Gas
1,003 MWAgreement signed Heard, GASoutheast Mar 2024target 2028
Gas project IC-1254a, Heard County
Gas
1,003 MWAgreement signed Heard, GASoutheast Mar 2024target 2028
Battery storage project Q112, San Bernardino County
Battery storage
1,000 MWIn study San Bernardino, CAWest Oct 2024target 2028
Zeus Spade Wind
Wind + storage · Spade Wind, LLC
987 MWIn study Mitchell, TXERCOT Mar 2024target 2027
EmberYork
Gas · EmberYork Energy Center
900 MWAgreement signed Austin, TXERCOT Aug 2024target 2028
Fierce River Solar
Solar + storage · Rio Grande Solar LLC
896 MWIn study Starr, TXERCOT Mar 2024target 2029
West Royal Natural Gas (TEF-Due Diligence)
Gas · Invenergy Energy Transition Development LLC
888 MWIn study Upton, TXERCOT Jun 2024target 2030
Solar + storage project Q2417, Maricopa County
Solar + storage
843 MWIn study Maricopa, AZWest Feb 2024target 2028
Replacing 864 MW of coal with Natural Gas Generators; Castle Bluff
Gas
824 MWIn study St. Louis, MOMISO May 2024target 2025
Solar + storage project Q2412, Navajo County
Solar + storage
822 MWIn study Navajo, AZWest Feb 2024target 2028
Zeus Mitchell Solar
Solar + storage · Mitchell Solar, LLC
805 MWIn study Mitchell, TXERCOT Mar 2024target 2029
Gas project 174, Pima County
Gas
800 MWIn study Pima, AZWest Jun 2024target 2027
Gas project 618, Stewart County
Gas
800 MWIn study Stewart, TNSoutheast Jun 2024target 2027
Gas project 622, Trousdale County
Gas
800 MWIn study Trousdale, TNSoutheast Jun 2024target 2031
Indigo Solar 3
Solar · Indigo solar 3
800 MWIn study Fisher, TXERCOT Oct 2024target 2028
Flint River 780 MW Unit
Gas
780 MWIn study Mitchell, GASoutheast Oct 2024target 2029
Gas project J3829, Hot Spring County
Gas
770 MWIn study Hot Spring, ARMISO Apr 2024target 2028
Gas project J3874, Union County
Gas
770 MWIn study Union, ARMISO Dec 2024target 2028
Axis Ridge Wind
Onshore wind · Axis Ridge Wind, LLC
750 MWIn study Sutton, TXERCOT Nov 2024target 2029
Central Power Station
Gas · Hydra-Gen Energy Unlimited
750 MWIn study Grimes, TXERCOT Mar 2024target 2027
Gas project GEN-2024-082, Williams County
Gas
745 MWIn study Williams, NDSPP Oct 2024target 2030
Gas project GEN-2024-081, Williams County
Gas
745 MWIn study Williams, NDSPP Oct 2024target 2029
Replacing 722 MW Coal with 285 MW of Battery and 437MW of Gas; Schahfer
Gas
733 MWIn study Jasper, INMISO Dec 2024target 2027
Gas project IC-1255, Bartow County
Gas
722 MWAgreement signed Bartow, GASoutheast Mar 2024target 2028
Gas project IC-1257, Bartow County
Gas
722 MWAgreement signed Bartow, GASoutheast Mar 2024target 2029
Gas project IC-1256, Bartow County
Gas
722 MWAgreement signed Bartow, GASoutheast Mar 2024target 2029
Gas project IC-1260, Effingham County
Gas
722 MWIn study Effingham, GASoutheast Mar 2024target 2031
Gas project IC-1264, Heard County
Gas
722 MWAgreement signed Heard, GASoutheast Mar 2024target 2029
Gas project IC-1258, Bartow County
Gas
722 MWAgreement signed Bartow, GASoutheast Mar 2024target 2029
Page 1 of 26

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)