United States › Grid › Interconnection queues › Texas
GAS · ERCOTEmberYork
EmberYork is a 900 MW gas request with a signed interconnection agreement in the ERCOT interconnection queue, in Austin County, Texas.
Queue statusConsented
- PlanningQueued Aug 2024 (completed)
- ConsentedDec 2025 (current stage)
- Construction (not yet reached)
- OperatingTarget Jan 2028 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 28INR0089
- Grid region
- ERCOT (Texas)
- Developer
- EmberYork Energy Center
- Connection point (POI)
- TAP 138kV WALLIS 44740 - GERBHRT 44700
- Location
- Austin County, Texas
- Technology
- Gas: 900 MW
- Total requested
- 900 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 29 August 2024
- Agreement signed
- 12 December 2025
- Proposed online date
- January 2028
Location
Marker shows the centre of Austin County; the queue data does not give exact sites.
Other requests in Austin County
- Sky Global West HoustonGas · 325 MW · agreement signed
- Symphony BESSBattery storage · 612 MW · in study
- Sunrose Renewable Energy Solar SLFSolar + storage · 310 MW · in study
- Homestead Power (TEF-Due Diligence)Gas · 260 MW · in study
- Saddlehorn Energy StorageBattery storage · 257 MW · in study
- Parula Energy CenterBattery storage · 251 MW · in study
- Prost ESSBattery storage · 203 MW · in study
- BremRaek BESSBattery storage · 201 MW · in study
- Pamplona StorageSolar + storage · 154 MW · in study
- Pamplona SolarSolar + storage · 42.4 MW · in study
- ELTEX Power StationGas · 488 MW · withdrawn
- WalstromGas · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem