United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTParula Energy Center
Parula Energy Center is a 251 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Austin County, Texas.
Queue statusIn planning
- PlanningQueued May 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 27INR0252
- Grid region
- ERCOT (Texas)
- Developer
- Parula Energy Center
- Connection point (POI)
- 7287 Bellville North 138kV
- Location
- Austin County, Texas
- Technology
- Battery: 251 MW
- Total requested
- 251 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 20 May 2024
- Proposed online date
- September 2027
Location
Marker shows the centre of Austin County; the queue data does not give exact sites.
Other requests in Austin County
- EmberYorkGas · 900 MW · agreement signed
- Sky Global West HoustonGas · 325 MW · agreement signed
- Symphony BESSBattery storage · 612 MW · in study
- Sunrose Renewable Energy Solar SLFSolar + storage · 310 MW · in study
- Homestead Power (TEF-Due Diligence)Gas · 260 MW · in study
- Saddlehorn Energy StorageBattery storage · 257 MW · in study
- Prost ESSBattery storage · 203 MW · in study
- BremRaek BESSBattery storage · 201 MW · in study
- Pamplona StorageSolar + storage · 154 MW · in study
- Pamplona SolarSolar + storage · 42.4 MW · in study
- ELTEX Power StationGas · 488 MW · withdrawn
- WalstromGas · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem