Homestead Power (TEF-Due Diligence)

Homestead Power (TEF-Due Diligence) is a 260 MW gas request in interconnection study in the ERCOT interconnection queue, in Austin County, Texas.

Queue statusIn planning
  1. PlanningQueued Jul 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
29INR0041
Grid region
ERCOT (Texas)
Developer
Homestead Power LLC
Connection point (POI)
138 kV New Bremen #7271
Location
Austin County, Texas
Technology
Gas: 260 MW
Total requested
260 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
30 July 2024
Proposed online date
December 2029

Location

Marker shows the centre of Austin County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Austin County