United States › Grid › Interconnection queues › Georgia
GAS · SOUTHEASTGas project IC-1258, Bartow County
Gas project IC-1258, Bartow County is a 722 MW gas request with a signed interconnection agreement in the Southeast interconnection queue, in Bartow County, Georgia, connecting to Southern Company.
Queue statusConsented
- PlanningQueued Mar 2024 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Sep 2029 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- IC-1258
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Plant Bowen Substation 500 kV Bus
- Location
- Bartow County, Georgia
- Technology
- Gas: 722 MW
- Total requested
- 722 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA Executed
- Queue status
- Active
- Entered queue
- 18 March 2024
- Proposed online date
- September 2029
Location
Marker shows the centre of Bartow County; the queue data does not give exact sites.
Other requests in Bartow County
- Gas project IC-1255, Bartow CountyGas · 722 MW · agreement signed
- Gas project IC-1257, Bartow CountyGas · 722 MW · agreement signed
- Gas project IC-1256, Bartow CountyGas · 722 MW · agreement signed
- Battery storage project IC-1222, Bartow CountyBattery storage · 250 MW · agreement signed
- Solar project IC-868, Bartow CountySolar · 200 MW · agreement signed
- Battery storage project 25-IC-1313, Bartow CountyBattery storage · 250 MW · in study
- Battery storage project IC-1144, Bartow CountyBattery storage · 260 MW · suspended
- Battery storage project IC-1245, Bartow CountyBattery storage · 575 MW · withdrawn
- Battery storage project IC-827, Bartow CountyBattery storage · 200 MW · withdrawn
- Battery storage project IC-1119, Bartow CountyBattery storage · 200 MW · withdrawn
- Battery storage project IC-934, Bartow CountyBattery storage · 100 MW · withdrawn
- Battery storage project IC-935, Bartow CountyBattery storage · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem