BATTERY STORAGE · SOUTHEAST

Battery storage project IC-1222, Bartow County

Battery storage project IC-1222, Bartow County is a 250 MW battery storage request with a signed interconnection agreement in the Southeast interconnection queue, in Bartow County, Georgia, connecting to Southern Company.

Queue statusConsented
  1. PlanningQueued Dec 2023 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
IC-1222
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Bowen - Judy Mountain 230 kV Line
Location
Bartow County, Georgia
Technology
Battery: 250 MW
Total requested
250 MW
Service type
Energy only (ERIS)
Study phase
IA Executed
Queue status
Active
Entered queue
19 December 2023
Proposed online date
June 2027

Location

Marker shows the centre of Bartow County; the queue data does not give exact sites.

Power plants in Georgia · Transmission lines in Georgia

Other requests in Bartow County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem