United States › Grid › Interconnection queues › California
OTHER · WESTOther project Q572, Riverside County
Other project Q572, Riverside County is a 1,300 MW other request in interconnection study in the West interconnection queue, in Riverside County, California, connecting to Arizona Public Service.
- PlanningQueued May 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget May 2031 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- Q572
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Arizona Public Service
- Connection point (POI)
- Delaney 500kV Switchyard/TS30 500kV Switchyard
- Location
- Riverside County, California
- Technology
- Other: 1,300 MW
- Total requested
- 1,300 MW
- Service type
- Network resource (NRIS)
- Study phase
- Phase 1 Cluster Study
- Queue status
- Active
- Entered queue
- 15 May 2024
- Proposed online date
- May 2031
Location
Marker shows the centre of Riverside County; the queue data does not give exact sites.
Power plants in California · Transmission lines in California
Other requests in Riverside County
- OberonSolar + storage · 1,037 MW · agreement signed
- Grace Energy CenterSolar + storage · 1,017 MW · agreement signed
- EasleySolar + storage · 940 MW · agreement signed
- Athos Power PlantSolar + storage · 908 MW · agreement signed
- Lycan SolarSolar + storage · 800 MW · agreement signed
- Calypso SolarSolar + storage · 800 MW · agreement signed
- Menifee Power BankBattery storage · 680 MW · agreement signed
- Twin Palms SolarSolar + storage · 576 MW · agreement signed
- RedondaSolar + storage · 542 MW · agreement signed
- CobaltSolar + storage · 513 MW · agreement signed
- Double Butte StorageBattery storage · 508 MW · agreement signed
- Lake Elsinore Advanced Pumped Storage ProjectBattery storage · 500 MW · agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem