United States › Grid › Interconnection queues › California

SOLAR + STORAGE · CAISO

Athos Power Plant

Athos Power Plant is a 908 MW solar + storage request with a signed interconnection agreement in the CAISO interconnection queue, in Riverside County, California, connecting to SCE.

Queue statusConsented
  1. PlanningQueued May 2017 (completed)
  2. ConsentedOct 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1405
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Red Bluff Substation 230kV
Location
Riverside County, California
Technology
Solar: 458 MW · Battery: 450 MW
Total requested
908 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
1 May 2017
Agreement signed
27 October 2025
Proposed online date
May 2027

Location

Marker shows the centre of Riverside County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Riverside County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem