🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

SOLAR + STORAGE · CAISO

Lycan Solar

Lycan Solar is a 800 MW solar + storage request with a signed interconnection agreement in the CAISO interconnection queue, in Riverside County, California, connecting to SCE.

Queue statusConsented
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedApr 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2030 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1643
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Red Bluff Substation 500kV
Location
Riverside County, California
Technology
Solar: 400 MW · Battery: 400 MW
Total requested
800 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
15 April 2019
Agreement signed
13 April 2023
Proposed online date
April 2030

Location

Marker shows the centre of Riverside County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Riverside County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem