United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in the USA (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown635117.0 GW
Active in queue117.0 GW635 requests
Agreement signed57.7 GW326 requests
Withdrawn1,752246.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

635 requests · page 1 of 13
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project G0648, Klamath County
Solar + storage
1,400 MWIn study Klamath, ORWest May 2020target 2026
BasRanch (TEF - Due Diligence)
Gas · CPV Basin Ranch, LLC
1,350 MWAgreement signed Ward, TXERCOT Aug 2020target 2028
Potentia-Viridi
Other
1,225 MWAgreement signed San Joaquin, CACAISO Apr 2020target 2028
Replace 1163.3 MW of Sabine Units 3, 4 & 1 with 2 on 1 Combined Cycle Gas Turbine facility; Sabine 1
Gas
1,166 MWIn study Orange, TXMISO Aug 2020target 2026
Windwalker Offshore
Offshore wind
1,029 MWAgreement signed San Luis Obispo, CACAISO Apr 2020target 2028
Grace Energy Center
Solar + storage
1,017 MWAgreement signed Riverside, CACAISO Apr 2020target 2027
Gas project GEN-2020-065, Gaines County
Gas
1,003 MWAgreement signed Gaines, NMSPP Apr 2020target 2028
Solar + storage project G0657, Klamath County
Solar + storage
1,000 MWIn study Klamath, ORWest Sep 2020target 2027
Arida 3 Solar Farm
Solar + storage
900 MWIn study Clark, NVCAISO Apr 2020target 2030
Purple Sage Energy Center
Solar + storage
817 MWAgreement signed Clark, NVCAISO Apr 2020target 2028
Solar + storage project Q76, Kern County
Solar + storage
800 MWIn study Kern, CAWest Mar 2020target 2023
Gas project 416, Colbert County
Gas
780 MWAgreement signed Colbert, ALSoutheast Feb 2020target 2022
Gas project 417, Muhlenberg County
Gas
780 MWAgreement signed Muhlenberg, KYSoutheast Feb 2020target 2022
Onshore wind project 391
Onshore wind
750 MWPaused / redesign West Aug 2020target 2023
Onshore wind project C012, Wheatland County
Onshore wind
750 MWIn study Wheatland, MTWest Jul 2020target 2023
Cedar Bayou 5 (TEF - Due Diligence)
Gas · NRG Cedar Bayou 5 LLC
697 MWAgreement signed Chambers, TXERCOT Mar 2020target 2027
Steel City Battery Storage
Battery storage
675 MWAgreement signed Contra Costa, CACAISO Apr 2020target 2029
Sunrise Power Improvement
Gas
656 MWIn study Kern, CACAISO Apr 2020target 2024
Pinnington Solar
Solar + storage · Hecate Energy Longhorn Solar LLC
654 MWAgreement signed Jack, TXERCOT Dec 2020target 2026
Solar + storage project GEN-2020-007, Linn County
Solar + storage
650 MWAgreement signed Linn, KSSPP Apr 2020target 2028
Willow Rock Energy Storage
Other
620 MWAgreement signed Kern, CACAISO Apr 2020target 2030
Harquahala Sunrise
Solar + storage
618 MWIn study Maricopa, AZCAISO Apr 2020target 2030
Skylab Solar
Solar · EDF Renewables Development, Inc.
610 MWIn study Wharton, TXERCOT Jun 2020target 2025
Cachena Solar SLF
Solar + storage · Clear Fork Creek Solar LLC
601 MWAgreement signed Wilson, TXERCOT May 2020target 2027
Battery storage project G0642, Crook County
Battery storage
600 MWIn study Crook, ORWest Feb 2020target 2025
Other project Company KR, White Pine County
Other
600 MWAgreement signed White Pine, NVWest Sep 2020target 2028
Battery storage project G0643, Crook County
Battery storage
600 MWIn study Crook, ORWest Feb 2020target 2024
Sanborn 5 Hybrid
Solar
560 MWAgreement signed Kern, CACAISO Apr 2020target 2027
Solar + storage project Q360, Maricopa County
Solar + storage
550 MWAgreement signed Maricopa, AZWest Sep 2020target 2023
Cobalt
Solar + storage
513 MWAgreement signed Riverside, CACAISO Apr 2020target 2027
Old Aqueduct Solar
Solar + storage · Old Aqueduct Solar
512 MWIn study Hale, TXERCOT Dec 2020target 2028
Bottom Grass Solar
Solar + storage · Bottom Grass Solar Project, LLC
509 MWAgreement signed Colorado, TXERCOT Nov 2020target 2028
Tabor Solar
Solar · Quanah Solar LLC
506 MWIn study Hardeman, TXERCOT Sep 2020target 2027
Frye Storage
Solar + storage · Hecate Energy Frye Storage LLC
504 MWIn study Swisher, TXERCOT Sep 2020target 2026
Pinnington Storage
Solar + storage · Hecate Energy Longhorn Storage LLC
503 MWIn study Jack, TXERCOT Dec 2020target 2029
Duffy Solar
Solar + storage · VDA Solar Texas 1 LLC
503 MWAgreement signed Matagorda, TXERCOT Sep 2020target 2027
Solar + storage project Q334, Maricopa County
Solar + storage
500 MWIn study Maricopa, AZWest Mar 2020target 2023
Other project 390, Yellowstone County
Other
500 MWIn study Yellowstone, MTWest Aug 2020target 2023
Solar + storage project 84, Pima County
Solar + storage
500 MWIn study Pima, AZWest Sep 2020target 2023
Battery storage project Q78, Kern County
Battery storage
500 MWIn study Kern, CAWest Oct 2020target 2021
Battery storage project G0656, Grant County
Battery storage
500 MWIn study Grant, WAWest Sep 2020target 2023
Solar project GEN-2020-087, Comanche County
Solar
500 MWIn study Comanche, OKSPP Apr 2020target 2026
Fourth Quarter
Battery storage · Fourth Quarter BESS, LLC
500 MWAgreement signed Montgomery, MDPJM Oct 2020target 2030
Calvada Springs Solar
Solar + storage
500 MWAgreement signed Inyo, CACAISO Apr 2020target 2027
Hawkins Solar Hybrid
Solar + storage
500 MWIn study Kern, CACAISO Apr 2020target 2027
Solar + storage project J1586, Calhoun County
Solar + storage
499 MWAgreement signed Calhoun, MIMISO Jun 2020target 2025
Baker Branch Solar
Solar · Mockingbird Solar Center, LLC
469 MWAgreement signed Lamar, TXERCOT Mar 2020target 2026
Dolphin Solar
Solar · Dolphin Solar LLC
450 MWIn study Fountain, INPJM Sep 2020target 2024
Solar + storage project Q337, Yavapai County
Solar + storage
450 MWIn study Yavapai, AZWest Mar 2020target 2027
Solar + storage project Q352, Navajo County
Solar + storage
450 MWIn study Navajo, AZWest Sep 2020target 2023
Page 1 of 13

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)