Solar project GEN-2020-087, Comanche County

Solar project GEN-2020-087, Comanche County is a 500 MW solar request in interconnection study in the SPP interconnection queue, in Comanche County, Oklahoma, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Apr 2020 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2020-087
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Cimmarron to Lawton 345 kV Line
Location
Comanche County, Oklahoma
Technology
Solar: 500 MW
Total requested
500 MW
Service type
NRIS and ERIS
Study phase
IA PENDING
Queue status
Active
Entered queue
23 April 2020
Proposed online date
October 2026

Location

Marker shows the centre of Comanche County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Comanche County