GAS · SPPGas project ERAS-2025-024, Comanche County
Gas project ERAS-2025-024, Comanche County is a 744 MW gas request in interconnection study in the SPP interconnection queue, in Comanche County, Oklahoma, connecting to AEP.
Queue statusIn planning
- PlanningQueued Oct 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Nov 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- ERAS-2025-024
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Comanche 138kV Substation
- Location
- Comanche County, Oklahoma
- Technology
- Gas: 744 MW
- Total requested
- 744 MW
- Service type
- NRIS and ERIS
- Study phase
- ERAS
- Queue status
- Active
- Entered queue
- 2 October 2025
- Proposed online date
- November 2029
Location
Marker shows the centre of Comanche County; the queue data does not give exact sites.
Other requests in Comanche County
- Solar + storage project GEN-2018-115, Comanche CountySolar + storage · 250 MW · agreement signed
- Solar project GEN-2017-171, Comanche CountySolar · 150 MW · agreement signed
- Solar project GEN-2017-173, Comanche CountySolar · 50.0 MW · agreement signed
- Solar project GEN-2017-172, Comanche CountySolar · 50.0 MW · agreement signed
- Gas project ERAS-2025-026, Comanche CountyGas · 744 MW · in study
- Solar project GEN-2020-087, Comanche CountySolar · 500 MW · in study
- Battery storage project GEN-2024-367, Comanche CountyBattery storage · 250 MW · in study
- Onshore wind project GEN-2008-037, Comanche CountyOnshore wind · 99.0 MW · built
- Onshore wind project GEN-2001-026, Comanche CountyOnshore wind · 74.3 MW · built
- Gas project GEN-2001-011, Comanche CountyGas · 900 MW · withdrawn
- Gas project GEN-2001-012, Comanche CountyGas · 600 MW · withdrawn
- Gas project GEN-2002-016, Comanche CountyGas · 354 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem