GAS Β· SPPGas project GEN-2001-012, Comanche County
Gas project GEN-2001-012, Comanche County is a 600 MW gas request withdrawn in the SPP interconnection queue, in Comanche County, Oklahoma, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2001 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2001-012
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- AEP
- Location
- Comanche County, Oklahoma
- Technology
- Gas: 600 MW
- Total requested
- 600 MW
- Service type
- Energy only (ERIS)
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 16 March 2001
Location
Marker shows the centre of Comanche County; the queue data does not give exact sites.
Other requests in Comanche County
- Solar + storage project GEN-2018-115, Comanche CountySolar + storage Β· 250 MW Β· agreement signed
- Solar project GEN-2017-171, Comanche CountySolar Β· 150 MW Β· agreement signed
- Solar project GEN-2017-173, Comanche CountySolar Β· 50.0 MW Β· agreement signed
- Solar project GEN-2017-172, Comanche CountySolar Β· 50.0 MW Β· agreement signed
- Gas project ERAS-2025-026, Comanche CountyGas Β· 744 MW Β· in study
- Gas project ERAS-2025-024, Comanche CountyGas Β· 744 MW Β· in study
- Solar project GEN-2020-087, Comanche CountySolar Β· 500 MW Β· in study
- Battery storage project GEN-2024-367, Comanche CountyBattery storage Β· 250 MW Β· in study
- Onshore wind project GEN-2008-037, Comanche CountyOnshore wind Β· 99.0 MW Β· built
- Onshore wind project GEN-2001-026, Comanche CountyOnshore wind Β· 74.3 MW Β· built
- Gas project GEN-2001-011, Comanche CountyGas Β· 900 MW Β· withdrawn
- Gas project GEN-2002-016, Comanche CountyGas Β· 354 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem