United States › Grid › Interconnection queues › California
SOLAR + STORAGE · CAISOCalvada Springs Solar
Calvada Springs Solar is a 500 MW solar + storage request with a signed interconnection agreement in the CAISO interconnection queue, in Inyo County, California, connecting to GLW.
Queue statusConsented
- PlanningQueued Apr 2020 (completed)
- ConsentedJun 2025 (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 1798
- Grid region
- CAISO (California)
- Utility / transmission owner
- GLW
- Connection point (POI)
- Trout Canyon Substation 230 kV
- Location
- Inyo County, California
- Technology
- Solar: 250 MW · Battery: 250 MW
- Total requested
- 500 MW
- Service type
- Network resource (NRIS)
- Study phase
- Executed
- Queue status
- Active
- Entered queue
- 15 April 2020
- Agreement signed
- 12 June 2025
- Proposed online date
- December 2027
Location
Marker shows the centre of Inyo County; the queue data does not give exact sites.
Power plants in California · Transmission lines in California
Other requests in Inyo County
- Sunbaked SolarSolar + storage · 1,024 MW · agreement signed
- Borderline SolarSolar + storage · 1,268 MW · withdrawn
- Campito PeakBattery storage · 566 MW · withdrawn
- Geothermal project Q103, Inyo CountyGeothermal · 500 MW · withdrawn
- Hidden Hills Solar 1Solar · 306 MW · withdrawn
- Solar project Q56, Inyo CountySolar · 300 MW · withdrawn
- Coso Solar 2Solar · 207 MW · withdrawn
- Solar project Q34, Inyo CountySolar · 200 MW · withdrawn
- Solar project Q09, Inyo CountySolar · 200 MW · withdrawn
- Avenida Del SulSolar · 151 MW · withdrawn
- Ridge Solar StorageSolar · 151 MW · withdrawn
- Solar project Q20, Inyo CountySolar · 138 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem