SOLAR Β· CAISO

Avenida Del Sul

Avenida Del Sul is a 151 MW solar request withdrawn in the CAISO interconnection queue, in Inyo County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2023 (completed)
  2. Withdrawn / abandonedNov 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
2243
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
INYOKERN 115 kV
Location
Inyo County, California
Technology
Solar: 151 MW
Total requested
151 MW
Service type
Energy only (ERIS)
Study phase
Caiso Cluster 15 Unvalidated
Queue status
Withdrawn
Entered queue
17 April 2023
Proposed online date
March 2029
Withdrawn
November 2025

Location

Marker shows the centre of Inyo County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Inyo County