🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

SOLAR + STORAGE · CAISO

Borderline Solar

Borderline Solar is a 1,268 MW solar + storage request withdrawn in the CAISO interconnection queue, in Inyo County, California, connecting to GLW.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2023 (completed)
  2. Withdrawn / abandonedMay 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
2242
Grid region
CAISO (California)
Utility / transmission owner
GLW
Connection point (POI)
TROUT CANYON 230 kV
Location
Inyo County, California
Technology
Solar: 638 MW · Battery: 630 MW
Total requested
1,268 MW
Service type
Energy only (ERIS)
Study phase
Caiso Cluster 15 Unvalidated
Queue status
Withdrawn
Entered queue
17 April 2023
Proposed online date
October 2028
Withdrawn
May 2025

Location

Marker shows the centre of Inyo County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Inyo County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem