GAS · ERCOT

Cedar Bayou 5 (TEF - Due Diligence)

Cedar Bayou 5 (TEF - Due Diligence) is a 697 MW gas request with a signed interconnection agreement in the ERCOT interconnection queue, in Chambers County, Texas.

Queue statusConsented
  1. PlanningQueued Mar 2020 (completed)
  2. ConsentedJan 2022 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0029
Grid region
ERCOT (Texas)
Developer
NRG Cedar Bayou 5 LLC
Connection point (POI)
40000 Cedar Bayou 345kV
Location
Chambers County, Texas
Technology
Gas: 697 MW
Total requested
697 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
26 March 2020
Agreement signed
10 January 2022
Proposed online date
December 2027

Location

Marker shows the centre of Chambers County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Chambers County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem