BATTERY STORAGE · ERCOT

APV Plumwood Storage

APV Plumwood Storage is a 201 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Chambers County, Texas.

Queue statusConsented
  1. PlanningQueued Mar 2022 (completed)
  2. ConsentedSep 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0285
Grid region
ERCOT (Texas)
Developer
APV Lonestar Energy LLC
Connection point (POI)
Tap 138kV 40171 Baytown - 40015Cedar Bayou Plant
Location
Chambers County, Texas
Technology
Battery: 201 MW
Total requested
201 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
30 March 2022
Agreement signed
3 September 2024
Proposed online date
May 2027

Location

Marker shows the centre of Chambers County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Chambers County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem