United States βΊ Grid βΊ Interconnection queues βΊ Texas
ONSHORE WIND Β· MISOOnshore wind project J1812, Chambers County
Onshore wind project J1812, Chambers County is a 294 MW onshore wind request withdrawn in the MISO interconnection queue, in Chambers County, Texas, connecting to ENTERGY TEXAS, INC..
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2020 (completed)
- Withdrawn / abandonedDec 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1812
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY TEXAS, INC.
- Connection point (POI)
- Stowell 230 kV
- Location
- Chambers County, Texas
- Technology
- Wind: 294 MW
- Total requested
- 294 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 25 June 2020
- Proposed online date
- September 2024
- Withdrawn
- December 2021
Location
Marker shows the centre of Chambers County; the queue data does not give exact sites.
Other requests in Chambers County
- Cedar Bayou 5 (TEF - Due Diligence)Gas Β· 697 MW Β· agreement signed
- APV Plumwood StorageBattery storage Β· 201 MW Β· agreement signed
- Coneflower Storage ProjectBattery storage Β· 171 MW Β· agreement signed
- Atria SolarSolar Β· 112 MW Β· in study
- Solar project J2952, Chambers CountySolar Β· 100 MW Β· in study
- Onshore wind project J2910, Chambers CountyOnshore wind Β· 303 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem