Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Atlas Complex Solar + storage |
4,357 MW | Agreement signed |
| Solar + storage project Q255, Coconino County Solar + storage |
2,000 MW | In study |
| Athos Power Plant Solar + storage |
908 MW | Agreement signed |
| Heritage Prairie Wind Onshore wind |
850 MW | Agreement signed |
| Park City Offshore Wind Offshore wind |
791 MW | Agreement signed |
| Hydro project G0566, Lincoln County Hydro |
646 MW | In study |
| Solar project IC-652, Sumter County Solar |
615 MW | Agreement signed |
| Tehuacana Wind Onshore wind |
600 MW | Paused / redesign |
| Gas project J732, Douglas County Gas |
562 MW | Under construction |
| Solar project GEN-2017-195, Johnson County Solar |
500 MW | Agreement signed |
| Ironwood Solar Solar + storage |
500 MW | Agreement signed |
| Solar + storage project IA-PNM-2017-13, San Juan County Solar + storage |
500 MW | Agreement signed |
| Onshore wind project G0558, Benton County Onshore wind |
500 MW | In study |
| Other project NC5-002, Clark County Other |
499 MW | In study |
| Whitehorse Wind Onshore wind ยท MESQUITE STAR SPECIAL LLC |
419 MW | Agreement signed |
| Onshore wind project GEN-2017-183, Hodgeman County Onshore wind |
400 MW | Agreement signed |
| Mount Laguna Wind 2 Onshore wind |
400 MW | Agreement signed |
| Driftwood Stella Solar + storage |
400 MW | Agreement signed |
| Solar project GEN-2017-108, Henry County Solar |
400 MW | Agreement signed |
| Solar project GEN-2017-184, Hodgeman County Solar |
400 MW | Agreement signed |
| Sonrisa Solar + storage |
384 MW | Agreement signed |
| Cottonwood Bayou Solar Solar ยท Cottonwood Bayou Solar, LLC |
351 MW | Agreement signed |
| Alle Catt II Wind Onshore wind ยท Alle-Catt Wind Energy LLC |
339 MW | In study |
| Myrtle Solar Solar ยท Myrtle Solar, LLC |
321 MW | Agreement signed |
| Solar project GEN-2017-210, Cedar County Solar |
310 MW | Paused / redesign |
| Horseshoe Bend Solar Solar ยท Clenera |
301 MW | In study |
| Onshore wind project J844, Knox County Onshore wind |
300 MW | Under construction |
| Solar project GEN-2017-239, Yoakum County Solar |
300 MW | Agreement signed |
| Solar + storage project 311, Yellowstone County Solar + storage |
300 MW | In study |
| Macadamia Solar Solar |
300 MW | Agreement signed |
| Onshore wind project GEN-2017-014, Haakon County Onshore wind |
300 MW | Agreement signed |
| Onshore wind project BHBE G13, Custer County Onshore wind |
300 MW | Agreement signed |
| Onshore wind project GEN-2017-151, Crosby County Onshore wind |
300 MW | Agreement signed |
| Solar + storage project TCS-09, Utah County Solar + storage ยท Longroad Development Company, LLC |
300 MW | Paused / redesign |
| Onshore wind project GEN-2017-181, Lancaster County Onshore wind |
300 MW | Agreement signed |
| Solar + storage project Q58, Kern County Solar + storage |
300 MW | In study |
| Firelands Wind Onshore wind |
298 MW | Agreement signed |
| Prairie Hill Wind Onshore wind ยท Prairie Hill LLC |
297 MW | Agreement signed |
| Onshore wind project GEN-2017-137, Oklahoma County Onshore wind |
295 MW | Agreement signed |
| Solar project J813, Clay County Solar |
275 MW | Under construction |
| Onshore wind project GEN-2017-175, Turner County Onshore wind |
270 MW | Agreement signed |
| Onshore wind project GEN-2017-158, Parmer County Onshore wind |
265 MW | Agreement signed |
| Onshore wind project GEN-2017-120, Dickinson County Onshore wind |
260 MW | Agreement signed |
| Onshore wind project GEN-2017-149, Johnston County Onshore wind |
258 MW | Agreement signed |
| Kontiki 2 Wind (ERNEST) Onshore wind |
250 MW | Paused / redesign |
| Kontiki 1 Wind (ERIK) Onshore wind |
250 MW | Paused / redesign |
| Onshore wind project J848, Christian County Onshore wind |
250 MW | Under construction |
| Solar project J815, Christian County Solar |
250 MW | Under construction |
| Solar project J877, Palo Alto County Solar |
250 MW | Under construction |
| Solar project GEN-2017-150, Grady County Solar |
250 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- SPP (Southwest Power Pool)66 ยท 11.8 GW
- West (non-ISO utilities)60 ยท 10.4 GW
- CAISO (California)17 ยท 8,678 MW
- ERCOT (Texas)36 ยท 5,724 MW
- MISO (Midcontinent)32 ยท 5,609 MW
- PJM (Mid-Atlantic, Midwest)44 ยท 4,774 MW
- Southeast (non-ISO utilities)28 ยท 2,517 MW
- ISO-NE (New England)3 ยท 831 MW
- NYISO (New York)6 ยท 749 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)