OFFSHORE WIND · ISO-NE

Park City Offshore Wind

Park City Offshore Wind is a 791 MW offshore wind request with a signed interconnection agreement in the ISO-NE interconnection queue.

Queue statusConsented
  1. PlanningQueued Dec 2017 (completed)
  2. ConsentedSep 2022 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2029 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
700
Grid region
ISO-NE (New England)
Connection point (POI)
Eversource 345 kV West Barnstable Substation
Location
Massachusetts
Technology
Offshore Wind: 791 MW
Total requested
791 MW
Service type
Energy only (ERIS)
Study phase
Executed
Queue status
Active
Entered queue
15 December 2017
Agreement signed
13 September 2022
Proposed online date
December 2029

Location

No county location in the queue data.