United States › Grid › Interconnection queues › Texas

ONSHORE WIND · SPP

Onshore wind project GEN-2017-151, Crosby County

Onshore wind project GEN-2017-151, Crosby County is a 300 MW onshore wind request with a signed interconnection agreement in the SPP interconnection queue, in Crosby County, Texas, connecting to SPS.

Queue statusConsented
  1. PlanningQueued Nov 2017 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2017-151
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
TUCO-Oklaunion 345kV
Location
Crosby County, Texas
Technology
Wind: 300 MW
Total requested
300 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
28 November 2017
Proposed online date
October 2026

Location

Marker shows the centre of Crosby County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Crosby County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem