United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· ERCOT

Wake Solar

Wake Solar is a 150 MW solar request suspended in the ERCOT interconnection queue, in Crosby County, Texas.

Queue statusPaused / redesign
  1. PlanningQueued Jul 2015 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2021 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
16INR0119
Grid region
ERCOT (Texas)
Developer
Invenergy
Connection point (POI)
59904 Cottonwood 345kV
Location
Crosby County, Texas
Technology
Solar: 150 MW
Total requested
150 MW
Study phase
FIS
Queue status
Suspended
Entered queue
19 July 2015
Proposed online date
December 2021
Withdrawn
October 2019

Location

Marker shows the centre of Crosby County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Crosby County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem