Onshore wind project GEN-2016-175, Crosby County

Onshore wind project GEN-2016-175, Crosby County is a 150 MW onshore wind request withdrawn in the SPP interconnection queue, in Crosby County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2016 (completed)
  2. Withdrawn / abandonedApr 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2016-175
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Border-TUCO 345kV
Location
Crosby County, Texas
Technology
Wind: 150 MW
Total requested
150 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 November 2016
Proposed online date
June 2020
Withdrawn
April 2020

Location

Marker shows the centre of Crosby County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Crosby County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem