ONSHORE WIND Β· ERCOTBlanco Canyon Wind
Blanco Canyon Wind is a 251 MW onshore wind request withdrawn in the ERCOT interconnection queue, in Crosby County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2016 (completed)
- Withdrawn / abandonedOct 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 18INR0034
- Grid region
- ERCOT (Texas)
- Developer
- Invenergy
- Connection point (POI)
- 59904 Cottonwood 345kV
- Location
- Crosby County, Texas
- Technology
- Wind: 251 MW
- Total requested
- 251 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 20 July 2016
- Proposed online date
- December 2021
- Withdrawn
- October 2019
Location
Marker shows the centre of Crosby County; the queue data does not give exact sites.
Other requests in Crosby County
- Onshore wind project GEN-2017-151, Crosby CountyOnshore wind Β· 300 MW Β· agreement signed
- Battery storage project GEN-2023-SR9, Crosby CountyBattery storage Β· 50.0 MW Β· agreement signed
- Wake Wind EnergyOnshore wind Β· 251 MW Β· in study
- Wake SolarSolar Β· 150 MW Β· suspended
- Onshore wind project GEN-2011-025, Crosby CountyOnshore wind Β· 80.0 MW Β· built
- Onshore wind project GEN-2016-120, Crosby CountyOnshore wind Β· 400 MW Β· withdrawn
- Onshore wind project GEN-2010-034, Crosby CountyOnshore wind Β· 261 MW Β· withdrawn
- Onshore wind project GEN-2013-017, Crosby CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project GEN-2016-175, Crosby CountyOnshore wind Β· 150 MW Β· withdrawn
- Onshore wind project GEN-2011-026, Crosby CountyOnshore wind Β· 19.7 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem