πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

ONSHORE WIND Β· SPP

Onshore wind project GEN-2013-017, Crosby County

Onshore wind project GEN-2013-017, Crosby County is a 200 MW onshore wind request withdrawn in the SPP interconnection queue, in Crosby County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2013 (completed)
  2. Withdrawn / abandonedOct 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2013-017
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Tap TUCO - OKU 345kV
Location
Crosby County, Texas
Technology
Wind: 200 MW
Total requested
200 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
29 March 2013
Proposed online date
December 2014
Withdrawn
October 2013

Location

Marker shows the centre of Crosby County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Crosby County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem