United States › Grid › Interconnection queues › California

SOLAR + STORAGE · CAISO

Sonrisa

Sonrisa is a 384 MW solar + storage request with a signed interconnection agreement in the CAISO interconnection queue, in Fresno County, California, connecting to PGAE.

Queue statusConsented
  1. PlanningQueued May 2017 (completed)
  2. ConsentedSep 2020 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1391
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Tranquility 230 kV
Location
Fresno County, California
Technology
Solar: 200 MW · Battery: 184 MW
Total requested
384 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
1 May 2017
Agreement signed
2 September 2020
Proposed online date
December 2026

Location

Marker shows the centre of Fresno County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Fresno County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem